Filings due after the AGM or incorporation

Set AOC-4, MGT-7 and ADT-1 AGM to fall due after each client's AGM, ADT-1 BM 30 days after incorporation, and enter each date once.

Open Compliance2 min readChecked 9 Nov 2026

AOC-4, MGT-7 and ADT-1 AGM are not due on a fixed date. They fall due a set number of days after each company's own AGM: AOC-4 30 days after it, MGT-7 60 days, ADT-1 AGM 15 days. Enter each client's AGM date once a year and their dates follow. ADT-1 BM, for the first auditor, falls due 30 days after the company's incorporation.

How it works

  1. Set the filing to follow the AGM. Open the filing, or click Add Compliance, set Schedule to Yearly and switch on Due after the client's AGM.
  2. Enter the days. Under Days after the AGM, type 30 for AOC-4, 60 for MGT-7, 15 for ADT-1 AGM, or 0 for the AGM itself. Save. The list reads, for example, 30 days after the AGM.
  3. Open the client's Work tab. When the client carries an AGM-linked filing, a line at the top reads AGM · FY 2025-26.
  4. Click Add AGM date (or Change). Pick the financial year, the AGM date and, if you like, the last board meeting date. Save.
  5. Check the tasks. That year's open tasks, reminders and the client's monthly calendar move to the new dates. The message after saving says how many tasks moved.

When the government extends the due date

MCA often extends the last date for AOC-4 and MGT-7. Enter the extended date once on the filing and it applies to every client on it, so nobody's filing shows as overdue on the old date.

  1. Open the filing. On the Compliance page, click the filing, for example Annual Return (MGT-7), to open Edit Compliance.
  2. Find the extension box. Under Days after the AGM is a box headed Government extended the due date?
  3. Pick the financial year and the extended date, then click Save extended date. You do not need to click Update Compliance for this.
  4. Check the result. The message says how many open tasks moved. The filing's row on the Compliance page reads Extended to and the date, and each task shows Extended by the government beside Due after AGM.

Each client's due date becomes the later of two dates: its own AGM plus the days, or the extended date. A client whose AGM was late enough to give a later date keeps that later date. Reminders and the client's calendar follow the new date. Finished tasks keep their date.

Set the extension separately on each filing it covers. AOC-4, MGT-7 and MGT-7A are separate filings, so if the notice extends all three, enter it on all three.

Made a mistake? Click Remove next to the year in the same box. Open tasks go back to the date the AGM gives.

ADT-1 BM and ADT-1 AGM

ADT-1 is two separate filings, and a company usually needs both:

  • First Auditor Appointment by Board (ADT-1 BM): the board appoints the first auditor within 30 days of incorporation. Filed once, due 30 days after the date of incorporation.
  • Auditor Appointment at AGM (ADT-1 AGM): the auditor appointed at the AGM, starting with the first AGM. Due 15 days after that AGM, and it moves if you change the AGM date.
  1. Switch both on for the client. On the client's Work tab, under Compliance, tick ADT-1 BM and ADT-1 AGM and give each one a person.
  2. Enter the date of incorporation. A line at the top of the Work tab reads Incorporated. Click Add incorporation date, pick the date and save. You can also set it under Edit on the client, and it is filled in for you when you enter the client's CIN.
  3. Check the task. ADT-1 BM's task is created, due 30 days after that date. The line reads, for example, ADT-1 BM due 31 Oct 2026.

Tips

  • Picking AOC-4, MGT-7, ADT-1 AGM or another standard AGM filing from the title list switches this on with the right number of days for you. Picking ADT-1 BM sets it to one-time, 30 days after incorporation.
  • You can also set the date from the task: an AGM-linked task shows a Due after AGM line with a Set AGM date link.
  • The calendar only lets you pick days from 1 April of the financial year you chose to the next 31 March, so a late AGM can still be entered on its real date. Other days are greyed out.
  • An extended date can be any day from 1 April of the AGM year to 31 December of the year after.
  • Only people with full Compliance access can add or change the AGM date, the incorporation date or an extended date. Others see the dates, without the buttons.

Common questions

The government extended MGT-7 but our tasks still show overdue.

The extended date has not been entered on the filing yet. Open Annual Return (MGT-7) on the Compliance page and use Government extended the due date? as described above. Every client's open MGT-7 task moves at once.

Our client held its AGM on 15 September. Why does AOC-4 still say 30 October?

The AGM date has not been entered, so the date assumes an AGM on 30 September (ADT-1 AGM 15 October, AOC-4 30 October, MGT-7 30 November). Add the AGM date on the client's Work tab and AOC-4 moves to 15 October, MGT-7 to 14 November and ADT-1 AGM to 30 September.

A task says "Assumed — AGM on 30 Sep". What do I do?

Click Set AGM date on that line, pick the client's AGM date and save. The due date changes and the word Assumed goes away.

Where did "Auditor Appointment (ADT-1)" go?

It is now called Auditor Appointment at AGM (ADT-1 AGM). The clients, people and dates on it stayed the same. First Auditor Appointment by Board (ADT-1 BM) was added beside it in your compliance list, switched on for no client until you tick it.

I switched on ADT-1 BM but no task appeared.

The client has no date of incorporation yet, so there is nothing to count 30 days from. The filing's card on the Work tab says No task yet: add the incorporation date with an Add date link, and the line at the top reads Not entered — no task until it is. Add the date and the task is created. If the 30 days ended more than six months ago, no task is made, because the filing is long past. The card says so. The same line appears on any switched-on filing that has no task, with the reason: nobody set to file it, no AGM date, or no due date.

I added a task called "ADT BM" myself. How do I connect it to the filing?

Open the client's Work tab, Compliance. A yellow box reads A task you made looks like a filing and names the task and the filing. Click Use this task. If the filing is not switched on yet, the button reads Switch on and use this task and does both. The filing then shows an Open task link to your task.

The company was incorporated this year. Why can't I pick an AGM date this year?

A company holds no AGM in the year it is incorporated. Its first AGM is due by 31 December of the next year. A company incorporated in 2026, in any month, holds its first AGM from 1 April 2027, due by 31 December 2027. The Work tab shows First AGM — due by 31 Dec 2027, and the AGM date window offers no earlier year. The year is read from the client's incorporation date or CIN, so check those on the client if the year looks wrong.

Why is there no AOC-4 or MGT-7 task for a company we just took on?

If the company was incorporated this year, it has no AGM this year, so AOC-4, MGT-7, ADT-1 AGM and other filings due after the AGM start from its first AGM year. A company incorporated in 2026 gets its first AOC-4 task for FY 2026-27, after its 2027 AGM. No task, reminder or calendar entry is made for the year before. Any task already created for that earlier year stays where it is, and you can delete it.

Do we have to enter the AGM date every year?

Yes, once per client per financial year. Changing it later moves the open tasks again. Finished tasks keep the date they were filed against. The incorporation date is entered only once.

More: Compliance · AOC-4 and MGT-7 drafts